S. No. Component Name of the City Project Name GoAP administrative sanction  Project Start Date Phy.
Prog.
(%) 
Fin. Prog. (Epd.)  Expected
Date of
Completion 
Remarks 
1 UIG Visakhapatnam WS to 32 peripherals  253.07   90% 151.44 Mar-16 Out of 46 reservoirs 41 completed, 5 are in progress.
42 MLD WTP completed  85 MLD WTP in progress. Out of 112 Km Feeder Mains 105 KM Laid. 555 KM distribution network completed.
Critical working condition in the location of reservoirs on hillocks.
2 UIG Visakhapatnam WS to North Eastern Zone  190.18   85% 147.00 Dec-15 Out of 10 ELSR/ GLSR's 6 no. completed, 4 are in progress.
Out of 526 KM distribution lines 410 Kms completed, balance in progress.
Out of 4 sumps 1 no. completed 3 are in progress. 
3 UIG Visakhapatnam WS to Old city  47.93   90% 39.00 Dec-15 Transmission Mains 11.25 Km completed 0.3 Km in progress. Out of 60 Km Distribution Lines 56 Km completed. Out of 3 ELSRs 1 no. completed balance in progress.
4 UIG Visakhapatnam Sewerage - Central Part  264.01   98% 246.00 Dec-15 Out of 311 Km Sewer Network 303 Km completed.
13 MLD STP completed.108 MLD STP 62% completed.7 Pumping Stations completed. Electro Mechanical Equipment for 3 nos. to be taken up.
Out of 27 Km Pumping Mains 22.5 Km completed.
 
Issue:Out of 5 Nos Railway Crossings, 1 No - Work in progress, 4 Nos - Permission required from Railway authorities, NH-5 crossing -1 No-to be taken up for up to which permission to be obtained. 
5 UIG Visakhapatnam BRTS Project  451.70   93% 410.00 Dec-15 PTC 90% completed. STC 94% completed. Adivivarum Jn. to Gosala (2Km) to be taken up.
Issue
1. LA at Adivivaram is pending due to dispute of ownership bet. SVLNS Devasthanum and Private Owners.
2. LA from private properties at Prndurthi, Baji jn., Marripalem, Vepagunta etc.
6 UIG Visakhapatnam WS 24X7 WS in South West Sectors  83.49   34% 27.00 Mar-16 Out of 24 Km Transmission lines 11
KM laid. Out of 96 Km Distribution
lines 17 KM Laid. Out of 8 GLSR/ MBR
2 nos. completed balance to be taken
up. Issue:
        * GoI could not release the Rs. 30 Crs. (2nd, 3rd & 4th Instl.) for the project.
         * As per Govt. memo revised scope is being finalized with bearest min. cost.
         * Revised targets will be fixed after approval of Govt.
7 UIG Vijayawada  UGD in Unserved areas 56.56   97% 51.73 Dec-15 No progress of 20 MLD STP at Jakkampudi & two pumping mains in I-town area for last two years due to paucity of funds.
8 UIG Vijayawada  UGD- Northern part 178.15   43% 77.35 Dec-15 20MLD STP at Jakkampudi nearing completion. 10 MLD STP at Auto nagar in progress.
Electro mechanical  components in progress.• Rider main 4 kms to be laid. 
9 UIG Vijayawada  BRTS 151.00   57% 86.69 Dec-15 Approches of Road Bridges a/c Eluru Canal and Budameru are in progress.
10 UIG Vijayawada  IRR 74.24   87% 111 Dec-15 • RoB works in progress. Removal of encroachments in Ramavarappadu area completed. Approch works are also in progress.
11 UIG Tirupati SWM 23.29   17% 5.00 Mar-16 Work completed to the extent of funds released.
12 UIG GVMC Procurement of Buses for Urban Transport System   - 102 Buses  46.95   35%   16.70   Mar-16 Purchase order placed for 57 buses. Target restricted by IA
13 UIG Vijayawada  Procurement of Buses for Urban Transport System  - 88 Buses 40.65   32% 13 Mar-16 Purchase order placed for 53 buses against 88 buses  sanctioned. 
14 UIG Guntur Procurement of Buses for Urban Transport System -  60 Buses 23.80   0% 0 Mar-16 Purchase order placed for 60 Buses
15 UIG Tirupati Procurement of 120 Buses for UT System under JnNURM   27.38   0% 0 Mar-16 Purchase order placed for 120 Buses.
16 UIG Chittoor Procurement of Buses for UT System - 30 Buses 9.15   0% 0 Mar-16 Purchase order placed for 30 Buses.
17 UIG Kadapa  Procurement of Buses for UT System - 40 Buses 18.20   0% 0 Mar-16 Purchase order placed for 40 Buses
18 UIG Ananthapur  APSRTC - Procurement of Buses for Urban Transport System  - 40 Buses 12.20   0% 0 Mar-16 Purchase order placed for 40 Buses
19 UIG Tirupathi Purchase of buses for Urban Transport as part of Second stimulas package  8.82   Completed   2010-2011  
20 UIG Tirupathi Storm Water Drains 45.56   Completed   31.03.2013  
21 UIG Tirupathi Under Ground Drainage 19.00   Completed   31.03.2012  
22 UIG Vijayawada Providing Sewerage System in Krishnalanka Area of Vijayawada 7.43 14.12.2006 Completed   07.08.2010  
23 UIG Vijayawada Providing sewege facilities in unserved areas  of VMC covering Housing Board Colony, Gunadala, Devinagar, Kaderaswarapet etc. 19.85 20.03.2007 Completed   31.12.2011  
24 UIG Vijayawada Providing sewrage treatment plan at Singhnagar (UASBR) (Sector-8) 9.49 19.11.2008 Completed   31.05.2011  
25 UIG Vijayawada Providing Water supply facilities in unserved areas 35.48 30.08.2006 Completed   30.06.2011  
26 UIG Vijayawada Restoration of roads damaged due to sewerage in VMC  36.26 25.06.2009 Completed   30.06.2011  
27 UIG Vijayawada Purchase of buses for Urban Transport as part of Second stimulas package 64.09   Completed   30.06.2011  
28 UIG Vijayawada Providing Storm Water Drains Mangalagiri Town to Vijayawada 30.16 25.08.2009 Completed   31.03.2013  
29 UIG Vijayawada SWD 49.12 03.01.2007 Completed   31.03.2015  
30 UIG Vijayawada WS - Augmentation 88.05   Completed   30.04.2015  
31 UIG Vijayawada SWM 58.05 17.01.2009  Completed   30.08.2015  
32 UIG Visakhapatnam Regularisation of S.L.Canal  3.39 22.09.2007 Completed   05.11.2008  
33 UIG Visakhapatnam Improvement of Yerrigedda storm water drain including bench drains 9.21 22.09.2007 Completed   25.06.2008  
34 UIG Visakhapatnam DPR for replacement of existing Thatipudi pipeline from Thatipudi reservoir to town service reservoir and pumping units  62.28 09.03.2007 Completed   09.06.2011  
35 UIG Visakhapatnam Providing Water Supply pipeline from TSR to Yendada and Kommadi Junction for augmenting water supply 23.40 09.03.2007 Completed   04.07.2009  
36 UIG Visakhapatnam Augmentation of drinking water supply to Gajuwaka area  39.76 05.06.2007 Completed   31.07.2012  
37 UIG Visakhapatnam Providing water supply distribution system to Gajuwaka area of GVMC (phase 2) 46.00 27.06.2008 Completed   31.07.2012  
38 UIG Visakhapatnam Providing Sewerage System in Old City Area 37.08 05.05.2007 Completed   31.10.2009  
39 UIG Visakhapatnam Purchase of buses for Urban Transport as part of Second stimulas package 55.29 2008-09 Completed   30.06.2011  
40 UIG Visakhapatnam Improvement of Storm  water drains for Zone.VIII of Greater Visakhapatnam City (Gangulhedda and Yerrigada branch canals) 72.27 2008-09 Completed   30.11.2013