Status of On-going Projects - BSUP
                  (Rs. in Cr.)
S.
No.
Component Name of the City Project Name GoAP administrative sanction  Project Start Date Phy.
Prog.
(%) 
Fin. Prog. (Epd.)  Expected
Date of
Completion 
Remarks 
1 BSUP Visakhapatnam - GVMC Slum Rehabilitation (Package II) (Housing and Civic Infrastructure in  6 Slums (7968 DUs) 167.12 03.01.2008 98% 156.44 Dec-15  Completed          -  6915 DUs.
 Progress              -  56 DUs
 Reinstated/ Dropped               -  997 DUs.
 Occupancy            -  4670 DUs .
 ACA drawn           -  Rs. 48.29 Cr.
 ACA to be drawn -  Nil. 

Infra in 2 locations in progress.  
2 BSUP Visakhapatnam - GVMC Slum Rehabilitation (Package I) (Housing and Civic Infrastructure in 22 slums (7352 DUs)  142.28 04.04.2007 99% 134 Dec-15  Completed           -  7232 DUs.
 Reinstated/ Dropped               -  120 DUs
 Occupancy           -  6232 DUs .
 ACA drawn           -  Rs. 45.33 Cr.
 ACA to be drawn -  Nil. 

Infra in 1 locations in progress. 
3 BSUP Vijayawada  3200 DUs in 100 blocks Opp Alankar Industries at Jakkampudi Village 36.54 21.07.2009 5% 0.99 Dec-16  Progress                  -  512 DUs
 Stopped                   - 384 DUs (Work terminated retenders to be invited)
 Dropped                   -  2304 DUs.
 Occupancy              -  Nil.
 ACA drawn               -  Rs. 19.89 Cr.

Infra -13 works in  tender stage
4 BSUP Vijayawada  3200 DUs in 100 blocks at Gollapudi, Jakkampudidi 98.05 21.07.2009 35% 13.96 Dec-16  Completed           -  320 DUs.
 Progress              -  2368 DUs ( Work terminated retenders to be invited)
 Dropped               -  512 DUs
 Occupancy           -  Nil.
 ACA drawn           -  Rs. 36.74 Cr.
 ACA to be drawn -  Rs. 4.41Cr. (Final Installment)
5 BSUP Vijayawada  15000 DUs - Rehabilitation of Flood Victims-Housing 372.90 20.12.2006 90% 336.56 Jun-16  Completed           -  12896 DUs.
 Progress              -  96 DUs
 Stopped               -  768 DUs,(Work terminated & retenders to be called for) 
 Dropped               -  1240 DUs
 Occupancy           -  9406 DUs .
 ACA drawn           -  Rs. 118.67 Cr.
 ACA to be drawn -  Nil. 

Infra -19 works in progress. In tender stage - Commercial complex.
6 BSUP Tirupati  3360 Housing & Infrastructural at Padipeta and Avilala-1 136.91   56% 77.26 Mar-16  Progress              -  3360 DUs.
 Occupancy           -  Nil.
 ACA drawn           -  Rs. 58.61 Cr.
 ACA to be drawn -  Nil. 

Rev. AS accorded by GoAP. Tenders received under evaluation for balance work.
7 BSUP Visakhapatnam - APSHCL 3616 houses in Aganampudi in GVMC Area 90.71 28.02.2009 85% 73.39 Mar-16  Completed           -  3616 DUs.
 Occupancy           -  2100 DUs .
 ACA drawn           -  Rs. 45.14 Cr.
 ACA to be drawn -  Nil. 

Offsite linkage for WS and Sewerage to be taken up. 
8 BSUP Visakhapatnam - APSHCL 1024 houses in Kommadi in GVMC Area 27.68 28.02.2009 85% 19.8 Mar-16 Completed           -  1024 DUs.
Occupancy           -  983 DUs .
ACA drawn           -  Rs. 13.77 Cr.
ACA to be drawn -  Nil. 

Infra. partly  completed.  Existing contract terminated.
For balance infra., works being grounded. 
9 BSUP Visakhapatnam - APSHCL 1839 houses with infrastructure facilities in Parwada in  GVMC   48.88 28.02.2009 82% 37.23 Mar-16 Completed           -  1839 DUs.
Occupancy           -  765 DUs .
ACA drawn           -  Rs. 24.29  Cr.
ACA to be drawn -  Nil. 
Infra. partly  completed.
Balance works being grounded. 
10 BSUP Visakhapatnam - APSHCL 2080 houses in Paradesi Palemin Survey No.178 in GVMC 48.79 28.02.2009 86% 41.45 Mar-16 Completed           -  2080 DUs.
Occupancy           -  1983 DUs .
ACA drawn           -  Rs. 24.32 Cr.
ACA to be drawn -  Nil.  
11 BSUP Visakhapatnam - APSHCL 544 houses in Paradesi Palemin Survey No.179 in  GVMC 12.75 28.02.2009 85% 10.06 Dec-15 Completed           -  544 DUs.
Occupancy           -  544 DUs .
ACA drawn           -  Rs. 6.26 Cr.
ACA to be drawn -  Nil. 

Infra in progress
Infra. partly  completed. The existing contract terminated. For balance infra. works are being grounded. 
12 BSUP Tirupati - APSHCL Housing Development at Vikruthamala of 1800 DUs in TMC 79.34   36% 37.38 Mar-16  Completed           - 984 DUs
 Not started        -  816 DUs
  (due to non-handing over of land)
 Occupancy           -  Nil.
 ACA drawn           -  Rs. 54.13 Cr.
 ACA to be drawn -  Nil. 

 Infra. In progress. 
13 BSUP Vijayawada Infrastructure Facilities in 8 Nos. Poor Settlements Circle -1 3.81 23.12.2006 Completed   31.03.2011  
14 BSUP Vijayawada Infrastructure in 22 Poor Settlements of central and northern parts of Vijayawada (Detailed designs and estimations for Basic Services to Urban Poor (Circle-II)) 59.83 31.05.2007 Completed   30.05.2011  
15 BSUP Vijayawada Infrastructure in 34 Poor Settlements of central and northern parts of Vijayawada (Detailed designs and estimations for Basic Services to Urban Poor (Circle-II & III) 26.48 31.05.2007 Completed   30.05.2011  
16 BSUP Vijayawada Detailed project report for repairs to dwelling units constructed under the VAMBAY in Ajit singh nagar, Vijayawada 7.74 30.06.2008 Completed   15.09.2009  
17 BSUP Vijayawada Housing-6752 DU's 248.69 31.01.2008 Completed   30.08.2015  
18 BSUP Visakhapatnam Infrastructure in Yetapalem 5.50 08.02.2007 Completed   30.03.2011  
19 BSUP Visakhapatnam Infrastructure in Srinagar 2.40 08.02.2007 Completed   30.03.2011  
20 BSUP Visakhapatnam Infrastructure in Vadlapudi 28.00 17.04.2007 Completed   30.06.2013  
21 BSUP Visakhapatnam Infrastructure in poor settelments of Aganampudi & Vambay colony and Madurawada 95.28 24.12.2007 Completed   30.06.2013  
22 BSUP Visakhapatnam Infrastructure in poor settelements of Pedagantyada, Gangavaram, TGR Nagar etc, in Gajuwaka 94.83 05.01.2008 Completed   30.06.2013