1 IHSDP Tirupati Construction of 4056 DUs at Tirupati Municipality 70.81   51% 49.60 Dec-16  Completed          -  2352 DUs.
 Progress              -  1704 DUs
 Occupancy          -  528 DUs .
 ACA drawn         -  Rs. 37.75 Cr.

Work in progress.
2 IHSDP Kakinada Construction of 3120 DUs at Kakinada (Ph.II) 67.56 21.01.2009 83% 25.20 Dec-16 Completed           -  1308 DUs.
Reinstated            -  1812 DUs
 Occupancy          -  Nil.
 ACA drawn         -  Rs. 14.29 Cr.
 ACA to be drawn - Rs. 14.29 Cr. 

Infra Works: 10 works completed
3 IHSDP Rajahmundry Construction of 3023 DUs at Rajahmundry (Satellite). 40.17 11.10.2006 88% 32.14 Sep-16

 Completed          -  2754 DUs.
 Progress              -  53 DUs

Ns                       - 216 (being Proposed for cancellation)

 Occupancy         -  2648 DUs .
 ACA drawn         -  Rs. 24.52 Cr.
 ACA to be drawn -  Nil. 

Infra works in progress.  

4 IHSDP Rajahmundry Construction of 2832 DUs at Rajahmundry Municipal Corporation 58.74 21.01.2009 95% 53.64 Dec-16 Completed           -  2832 DUs.
 Occupancy          -  480.
 ACA drawn         -  Rs. 29.40  Cr.
 ACA to be drawn -  Nil. 

Infra works in progress.  
5 IHSDP Guntur Construction of 2432 DUs at Guntur  47.75   100% 38.76 Dec-16 Completed           -  2432 DUs.
 Occupancy           -  Nil.
 ACA drawn           -  Rs. 24.47 Cr.
 ACA to be drawn -  Nil. 

Infra works to be completed.  
6 IHSDP Gudur  Construction of 1536 DUs at Guduru Municipality 21.96 21.03.2007 90% 15.16 Dec-15 Completed           -  1344 DUs.
 Progress              -  192 DUs
 Occupancy           -  748 DUs .
 ACA drawn           -  Rs. 9.56 Cr.
 ACA to be drawn -  Nil. 

Bidders not qualified. Notification issued for 3rd call.  
7 IHSDP Kurnool Construction of 2112 DUs at Kurnool Municipality 21.24   91% 20.67 Dec-15 Completed           -  2054 DUs.
 Progress              -  58 DUs
 Occupancy           -  615 DUs .
 ACA drawn           -  Rs. 16.99 Cr.
 ACA to be drawn -  Nil. 

Infra works to be completed.
8 IHSDP Rajampet  Construction of 510 DUs at Rajampeta Municipality 6.07 11.10.2006 90% 5.07 Dec-15  Completed           -  506 DUs.
 Progress              -  4 DUs
 Occupancy           -  411 DUs .
 ACA drawn           -  Rs. 4.50  Cr.
 ACA to be drawn -  Nil. 

Infra are in progress.
9 IHSDP Rayachoti  Construction of 1013 DUs at Rayachoty Municipality 14.54 11.10.2006 90% 9.42 Dec-15 Completed           -  977 DUs.
 Progress              -  36 DUs
 Occupancy           -  977 DUs .
 ACA drawn           -  Rs. 9.57  Cr.
 ACA to be drawn -  Nil. 

Infra are in progress.
10 IHSDP Samalkota Construction of 888 Dus at Samalkota Ph-11 23.85   Not Started      In 163rd CSC meeting dtd. 17.09.2015, at Samalkota -888 Dus reinstated in IHSDP Projects.
11 IHSDP Chittoor Revision in sanctioned DPR: Provision of infrastructure facilities at YSR Nagar at Chittoor 3.73 03.07.2008 Completed   31.08.2013  
12 IHSDP Madanapalli Revision in sanctioned IHSDP project at Madanapalle, Chittor Dist 4.29 17.02.2009 Completed   30.06.2011  
13 IHSDP Kakinada Providing infrastructure facilities to Jagannadhapuram Layout under IHSDP scheme in Kakinada Municipal Corporation 11.79 28.11.2008 Completed   31.03.2013  
14 IHSDP Kakinada Construction of 662 Houses at Kakinada, East Godavari Dist 10.70 11.10.2006 Completed   30.06.2014  
15 IHSDP Ramachandrapuram Revision in sanctioned IHSDP scheme for Construction of 720 Houses at Ramachandrapuram, East Godavari Dist. 9.62 11.10.2006 Completed   28.02.2014  
16 IHSDP Peddapuram Construction of 1416 DUs at Peddapuram Municipality 28.18 21.01.2009 Completed   28.02.2015  
17 IHSDP Samrlakota Construction of 912 DUs at Jaggammagaripeta, Samalkota Municipality 17.02 21.01.2009 Completed   28.02.2015  
18 IHSDP Bapatla Revision in sanctioned IHSDP project for provision of infrastructure facilities to slums in Bapatla, Guntur 8.32 29.11.2008 Completed   30.06.2012  
19 IHSDP Chilakaluripet Revision in sanctioned IHSDP project for provision of infrastructure facilities in 33 slums at Chilakaluripeta, Guntur Dist, 15.38 07.11.2008 Completed   31.03.2013  
20 IHSDP Guntur Standalone infrastructure improvement in existing slums in Guntur 19.83   Completed   30.08.2014  
21 IHSDP Macherla Revision in sanctioned IHSDP scheme for provision of infrastructure facilities for 13 slums in Macherla Mplty. 16.81 10.11.2008 Completed   31.03.2013  
22 IHSDP Narasaraopet Revision in sanctioned IHSDP project for provision of infrastructure facilities in 41 slums at Narasaraopet, Guntur Dist, A.P 19.67 22.10.2008 Completed   31.03.2013  
23 IHSDP Ponnur Revision in sanctioned IHSDP project for provision of infrastructure facilities in 25 slums at Ponnur, Guntur Dist. 13.27 28.07.2010 Completed   27.03.2013  
24 IHSDP Repalle Revision in sanctioned IHSDP project for provision of infrastructure facilities in 25 slums at Repalle, Guntur Dist. 5.82 08.06.2009 Completed   30.06.2012  
25 IHSDP Sattenapalli Revision in sanctioned IHSDP project for provision of infrastructure facilities in 22 slums at Sattenapalli, Guntur Dist. 14.10 29.11.2008 Completed   30.06.2012  
26 IHSDP Tenali Revision in sanctioned IHSDP project for provision of infrastructure facilities in 23 slums at Tenali, Guntur Dist., A.P 5.16 09.04.2009 Completed   31.03.2013  
27 IHSDP Vinukonda Revision in sanctioned IHSDP project for provision of infrastructure facilities in 34 slums at Vinukonda, Guntur Dist. 14.71 07.11.2008 Completed   31.03.2013  
28 IHSDP Kadapa Revision in sanctioned IHSDP project for provision of infrastructure facilities in Kadapa (Ph.II) Dist. 9.38 28.02.2009 Completed   30.11.2012  
29 IHSDP Kadapa Standalone infrastructure facilities at Azadnagar Housing Colony, Kadapa 2.23 15.07.2009 Completed   30.08.2014  
30 IHSDP Kadapa Standalone infrastructure facilities at Mamillapalli Housing Colony, Kadapa 5.84 15.07.2009 Completed   30.08.2014  
31 IHSDP Kadapa Revision in sanctioned IHSDP scheme for Construction of 600 DU's & infrastructure facilities at Buggavanka, Kadapa  6.94 28.09.2006 Completed   30.09.2014  
32 IHSDP Kadapa  Const.of 534 Houses and providing infrastructure facilities,Mruthunjayakunta, Kadapa  8.18 28.09.2006 Completed   30.06.2014  
33 IHSDP Proddatur Construction of 1500 DUs at Proddatur 18.12 11.10.2006 Completed   30.06.2014  
34 IHSDP Pulivendula Revision in sanctioned IHSDP project for provision of infrastructure facilities at Pulivendula, Kadapa Dist. 14.69 28.02.2009 Completed   31.03.2013  
35 IHSDP Machilipatnam Revision in sanctioned IHSDP project for provision of infrastructure facilities at Machilipatnam town, Krishna Dt. 9.17 14.09.2010 Completed   30.06.2012  
36 IHSDP Adoni Revision of sanctioned IHSDP scheme under JnNURM - Providing infrastructure facilities and basic amenities in Indiramma colonies at Adoni, Kurnool Dist, AP 4.75 26.09.2008 Completed   31.12.2012  
37 IHSDP Dhone Standalone infrastructure facilities in 8 slums at Dhone 1.12   Completed   31.08.2014  
38 IHSDP Kurnool Revision in sanctioned IHSDP project for providing infrastructure facilities and basic amenities in slums of Kurnool Municipal Corporation, Kurnool Dist, (Ph.II) 18.55 24.10.2009 Completed   31.03.2013  
39 IHSDP Kavali IHSDP Project for provision of infrastructure facilities at Girijanapalem slum (Ice Factory) at Kavali Phase lI, Dist. 3.47 02.10.2008 Completed   31.01.2011  
40 IHSDP Kavali IHSDP Project for provision of infrastructure facilities at Satellite township Budamagunta layout for relocating 680 houses of Kavali Municipality at Kavali, Nellore District. AP (Phase I) 1.53 18.10.2008 Completed   31.01.2011  
41 IHSDP Chirala IHSDP Project for provision of infrastructure facilities at 12 slums at Chirala, Prakasam Dist. 3.47 07.01.2009 Completed   31.08.2013  
42 IHSDP Ongole Standalone infrastructure facilities at 14 slums at Ongole, Prakasam dist 2.33 07.01.2009 Completed   30.08.2014  
43 IHSDP Anakapalle Construction of 384 houses for slum dwellers in Anakapalle municipality 1.65 27.02.2007 Completed   31.01.2011  
44 IHSDP Anakapalli Revision in sanctioned IHSDP project for Providing infrastructural facilities in slums of Anakapalle Municipal Aread (Ph.II), by PHED, Visakhapatnam 3.50 15.10.2008 Completed   31.12.2012  
45 IHSDP Bheemunipatnam Standalone infrastructure facilities at 39 slum at Bheemunipatnam 3.39 12.11.2008 Completed   30.08.2014